Article: GLF Schools: 191 Interactive Displays Across 26 Schools

GLF Schools: 191 Interactive Displays Across 26 Schools
GLF Schools is a multi academy trust of 43 schools, serving around 17,000 pupils across Surrey, Oxfordshire, Berkshire, Hampshire, West Sussex and London. In 2025 Simply AVS supplied and installed 191 interactive displays across 26 of the Trust's schools, replacing end-of-life whiteboards, projectors and speakers.
Project Overview
In January 2025 the Trust ran a competition through a public-sector framework to replace ageing classroom equipment, and awarded the contract to Simply AVS. The tender estimated up to 130 displays. By December 2025 the programme had grown to 191, as more schools joined and existing schools ordered further rooms.
Key Requirements
- 4K education displays: 75" for secondary classrooms and 65" for primary
- A five-year warranty on every display
- AirPlay casting and a soundbar of at least 60 W
- A cable kit run through trunking to a faceplate at the teacher's desk
- Old equipment decommissioned, removed and recycled
- Every display tested with the classroom device before sign-off
- Deliveries on weekdays between 9am and 3pm, installation within 72 hours of delivery, old equipment removed within a week, and WEEE certificates within 30 days
Project Scope & Solution
The programme covered supply, delivery, installation and commissioning in every room, plus removal of the equipment being replaced.
Displays & Audio
Simply AVS supplied Hikvision 65" and 75" interactive displays, each with a Hisense soundbar. Schools that wanted a higher specification chose Hikvision's Ultra panels.
Teacher Connection
Each room has new trunking and a faceplate at the teacher's desk with two HDMI ports and a USB connection for touch, so every classroom works the same way.
Removal & Recycling
Our team took down the old whiteboards, projectors and speakers and recycled them under WEEE regulations. Packaging was cleared from site, so schools were left with nothing to dispose of.
Additional Work
Alongside the main programme we relocated existing displays and carried out hall AV work, including projector installation at Glyn School, which has its own case study.
Project Challenges
The Trust's service levels were demanding, and its schools are widely spread.
Schools Spread from Banbury to Croydon
We grouped deliveries and installations by area to keep teams local. The first phase ran in five weekly delivery waves, with stock arriving mid-week so that installation fell within the 72-hour window.
Working Around the School Day
Some schools could release only one room at a time, early in the day or after 3pm. We built a room-by-room schedule with each school, recording the room, the agreed date and the member of staff who confirmed it, and moved larger work to the holidays. The summer phase used two teams working in parallel, each based near a cluster of schools.
Changes During the Programme
When schools asked for higher-specification panels, room moves or a mobile stand, we quoted and agreed each change before starting, so the main programme stayed on schedule.
Results
- The full tendered quantity of 130 displays was installed at 19 schools between March and May 2025.
- The summer phase, including seven schools new to the programme, finished by 26 August, before pupils returned.
- In total, 191 displays were installed across 26 schools by December 2025, 47% more than the original estimate.
- Follow-on work has included hall AV and network cabling.
"Simply AVS installed 191 interactive displays across 26 GLF schools in 2025. They planned each installation around the school day, kept our schools and IT team informed throughout, and finished the summer phase before pupils returned. We would be happy to work with them again."
Andrew Davies, Head of Operations, GLF Schools
Installed Equipment
- Hikvision 65" and 75" 4K interactive displays
- Hikvision Ultra series displays in selected rooms
- Hisense soundbars
- Wall brackets, trunking and cable kits
- Teacher faceplates with two HDMI ports and USB for touch
Project Photos
Delivery. Hikvision 65" displays and Hisense soundbars staged in a school hall. Deliveries ran in weekly waves so installation followed within 72 hours.
Removal. Old interactive displays taken down and removed from site for recycling under WEEE regulations.
Clean site. Packaging cleared from site for recycling, so schools were left with nothing to dispose of.
Finished room. Display and soundbar wall-mounted, with all cabling run neatly in trunking.
Neat cabling. Trunking takes the cables from the display down to the wall sockets, with nothing left loose.
Connected and tested. Each display was tested with the classroom PC on the Trust network before the school signed off the room.
In use. A primary maths lesson on a newly installed display.
Hall AV. Projector work at Glyn School, carried out from a tower scaffold in an empty hall.